Skip to content

Tulum guide

Electricity, CFE and Utilities in Tulum

Power out? Check your own breaker, then report it to CFE on 071 — any hour, any day. Getting it back on is free. Below: paying the bill, reconnection, putting the contract in your name, high bills and DAC, solar, water and gas — every answer with its official source.

Checked October 11, 202629 sources

The Power Is Out: What to Do Now

Check your own breaker first. If it’s on, report the outage to CFE: call 071 (24 hours, every day), or use the CFE Contigo app or Mi CFE. Restoring power is free.

  1. Check that your main breaker is on and nothing has tripped — CFE asks you to check this before you report.
  2. See whether neighbours are out too: TulumTown’s Local Updates show the outages people are reporting right now. You can post one in a minute.
  3. Report it to CFE: dial 071 from any phone, or use the CFE Contigo app or Mi CFE (app.cfe.mx). The app’s listing says you can follow a “No luz” report through each stage, from received to restored.
  4. Give your service number (top right of your bill) — or the account number, meter number, address or account holder’s name.
Have ready
  • Your service number (top right of the bill)
  • The full address with cross streets, colonia and postal code
  • A landmark
  • A phone number

CFE won’t act on a report if the service is suspended for non-payment or the fault is inside the home — that’s a job for an electrician. CFE lists no WhatsApp number on its official site (checked 11 Oct 2026). Restoration is free: if someone claiming to be CFE asks for money to restore your power, don’t pay — call 071.

More detail · 2 paragraphs

CFE’s own maximum times: up to 10 hours for one home in town (30 in rural areas), and up to 4 hours (10 rural) when a whole sector is out. Those are CFE’s stated limits, not a promise during storms.

An interruption that wasn’t force majeure: CFE’s supply contract says that, if you claim, it credits your bill with twice what the electricity you missed would have cost, within 15 business days of your claim.

Sources[1][2][3][4][10]

Pay Your CFE Bill

Pay in the CFE Contigo app or online in Mi CFE (bank cards), at a CFEmático machine — CFE’s Tulum office lists one open 24 hours — or at the banks and stores CFE authorizes. CFE says these options have no extra charge.

  1. Create a user and password on CFE’s portal (Mi CFE).
  2. Add your service under “Mis recibos registrados”.
  3. Choose “pago en línea”. CFE says a payment is registered within 48 hours at most — call 071 to check it arrived.
Reading your bill
  • No. de servicio (top right) — you need it for everything
  • TARIFA — your tariff
  • Límite de pago — the due date
  • Corte a partir — the date service can be suspended if unpaid
  • Periodo facturado — CFE’s sample household bill is bimonthly; check yours
  • DAP — Derecho de Alumbrado Público, a public-lighting charge set by local law, not by CFE

CFE never emails you a link to pay on a website. Pay only in the app, on app.cfe.mx or cfe.gob.mx, or in person.

More detail

CFE’s sample bill shows OXXO, 7-Eleven, Walmart, Sam’s Club, Banorte, Banco Azteca, BBVA and Telecomm as authorized places to pay; the list printed on your own bill is the one that applies. The app also offers a recurring charge, payment reminders and a paperless bill.

Sources[7][8][4][9][18]

Cut off for an Unpaid Bill: Getting Reconnected

Service can be suspended from the “Corte a partir” date on your bill. To reconnect, pay what you owe plus the reconnection fee, then call 071 — CFE says power comes back within a day in town.

CFE’s reconnection fee for a home (with 16% VAT)
  • Billed every two months, one wire: $80
  • Billed monthly, one wire: $58
  • Two or three wires: $91
More detail

Go by the dates on your own bill: CFE’s published contract allows suspension 30 calendar days after the due date, but its sample bill puts “Corte a partir” one day after “Límite de pago”. If a suspension isn’t fixed within 15 days, CFE can end the contract — so pay within those 15 days. Outside town, CFE allows up to three days to reconnect.

Sources[9][10][11]

A New Contract, or Putting It in Your Name

A new contract is free — you pay a guarantee deposit with the first bill. To put an existing contract in your name, go in person to a CFE office with your ID, a correct proof of address and a document showing ownership or possession of the property.

For a new home contract, CFE asks for
  • Official ID
  • The full address with cross streets
  • Your RFC (tax number)
  • A phone number and email
  • A finished electrical installation, with the nearest pole within 35 m in town
  • If someone applies for you: a simple or notarized carta poder and both IDs

Renting? CFE accepts proof of possession, not only ownership, and accepts a lease as proof of use in related procedures — bring your lease and ID, and confirm with 071 or the office first. CFE doesn’t say whether a foreign passport or residency card counts as “official ID” for a home contract, or what happens if you have no RFC: ask before you go.

More detail · 3 paragraphs

Apply at a CFE office or on CFE’s electronic contracting portal; CFE says it takes 2 days in town. The guarantee deposit for a home in 2026, one wire: $228 if you’re billed every two months, $114 monthly (October amounts; it changes slightly by month).

No power line nearby, the nearest pole more than 35 m away (50 m in rural areas), or you need three-phase power? First file a feasibility request (solicitud de factibilidad) at a CFE office: CFE checks whether it can supply you from the existing network or what works are needed, and their budget.

Moving house: you need a new contract at the new address, and should ask CFE to end the old one at least 5 business days before you leave.

Sources[14][15][16][6][17][19]

A High Bill, DAC, and How to Dispute It

Check the TARIFA line on your bill. If your average use over the last 12 months goes above your tariff’s limit, CFE moves you to DAC — a high-consumption rate with no government subsidy. You return to your normal rate once the 12-month average drops below the limit.

DAC limits (average kWh per month)
  • Tariff 1: 250
  • 1A: 300
  • 1B: 400
  • 1C: 850
  • 1D: 1,000
  • 1E: 2,000
  • 1F: 2,500

If you filed a complaint with CFE or Profeco before your power was suspended, CFE must restore it and can’t suspend it during the conciliation — unless the complaint is about the suspension itself.

More detail · 2 paragraphs

CFE assigns tariffs by locality, from summer temperatures, so neighbouring areas can differ — and CFE doesn’t publish Tulum’s tariff on a page we could find. Read your own bill. The colour bar on the bill is CFE’s DAC gauge: CFE recommends staying below its middle.

If you think the bill is wrong: report it to CFE (071, the app, the website or the office) and ask for a review of your meter — the first one in any 12 months is free. CFE should answer a complaint within 10 business days. Still unresolved? File it with Profeco: CFE takes part in Concilianet (online), or call 800 468 8722.

Sources[12][9][13][10][20][21]

CFE’s Office in Tulum

CFE’s office locator lists CASC Tulum at Calle Centauro Norte, Tulum Centro, 77760, with a CFEmático open 24 hours. CFE doesn’t publish the office’s opening hours there — call 071 before you go.

Bring your service number and ID. Name changes, damaged-appliance claims and solar interconnection requests are done at an office window.

Sources[18][4]

Solar Panels: Connecting to CFE

Rooftop solar under 0.7 MW needs no generation permit. You sign an interconnection contract with CFE, and signing it is free. With net metering, the energy you send to the grid is subtracted from your consumption.

CFE asks for
  • The interconnection request form
  • A location sketch
  • A single-line diagram
  • The technology’s data sheet
  • The inverter’s data sheet and certificate
  • Your latest paid bill, or your RMU code
More detail · 2 paragraphs

CFE offers three models: net metering (what you generate is subtracted from what you use), net billing (it isn’t subtracted; it’s settled separately) and total sale. Requests go in at a CFE office window; CFE allows up to 13 business days (18 with a technical opinion), not counting construction. A grid evaluation may cost extra.

Who pays for the two-way meter isn’t stated on the official pages we checked — ask your installer and CFE before you sign.

Sources[22][23][24]

Fallen Cables, Sparks and Trees on the Line

Keep well away from fallen cables, damaged poles or exposed equipment — CFE’s minimum safety distance from power lines is 2.5 metres — don’t touch them, and report them on 071. If someone is hurt or there’s a fire, call 911.

A tree touching the cable into your house: call 071 and ask for a “libranza” — a scheduled temporary disconnection — so it can be trimmed safely, then call 071 again to be reconnected. For electrical work at home, ask 071 or the office for a temporary disconnection at least 5 days ahead.

Sources[5][6]

An Outage Damaged an Appliance

If a CFE fault damaged an appliance, claim within 15 business days, in person at a CFE office (book it by calling 071). The claim is free; CFE answers within 10 business days, and any payment or repair depends on its decision.

Bring
  • Your bills paid up to date — CFE requires it
  • The account holder’s ID (or a carta poder and both IDs if someone goes for them)
  • A short letter describing what happened
  • Proof of ownership — or, if you’re not the account holder, proof you use the property (a lease, for example)
  • CFE’s claim form for damaged appliances
Sources[19][6]

Water: CAPA

Tulum’s water service is CAPA, Quintana Roo’s state water commission. Pay online through CAPA’s payment site; for contracts, bills and leaks, the Tulum office is on Avenida Tulum, Tulum Centro — its numbers are in Tulum Essentials.

For a new water connection, the state catalog lists
  • ID (INE or a valid passport)
  • The property deed, or an occupancy order
  • A current clave catastral (cédula from the municipal cadastre)
  • A location sketch
  • A written request (filled in at the office)

Changing the account holder, the no-debt certificate, disputes and water trucks are in the full water guide. Call CAPA before you go.

Sources[25][26]

Gas: LP Prices and Complaints

LP gas is sold by private companies, but the federal energy commission (CNE) publishes maximum prices every week, region by region — Tulum is in region 159. Check the current week’s table before you pay.

Short weight or overcharging: tell Profeco at denunciasgaslp@profeco.gob.mx with the truck’s number, or call 800 468 8722.

Sources[27][28][21]

Hurricanes and Long Outages

When a hurricane arrives, federal advice is to unplug appliances, switch off the main breaker, and close the gas and water valves. Use battery lamps, not candles. Afterwards, keep away from cables and report them on 071.

Sources[29][5]
How long should CFE take to restore power?

CFE’s stated maximums: 10 hours for one home in town (30 rural); 4 hours (10 rural) when a whole sector is out. [2]

Do retirees or pensioners get a discount?

No. CFE says it offers no special discounts; the household subsidy is applied automatically to every residential bill. [6]

How do I get a tax invoice (CFDI) for my bill?

Update the fiscal data on your account — RFC, name, fiscal address, tax regime and CFDI use — exactly as they appear on your current SAT Constancia de Situación Fiscal. [6]

How do I know my payment arrived?

CFE says a payment is registered within 48 hours at most; call 071 to check. [8]

Someone is stealing power (a “diablito”). Who do I tell?

Call 071. CFE says the report can be anonymous if you ask. [6]

My use went down. When do I leave DAC?

When your 12-month average falls below your tariff’s limit, CFE applies your normal household tariff again — because it’s a rolling average, that can take months. [12]

What is the service number?

Your identification in CFE’s system, printed at the top right of the bill. Have it ready for any request. [9]

Is CFE’s website cfe.mx?

cfe.mx now redirects to cfe.gob.mx; the customer apps (Mi CFE, tariffs, office locator) are on app.cfe.mx. [3]

  • TulumTown isn’t CFE, CAPA or any authority. This guide summarizes their public pages as checked on the date above; procedures and fees change, and the official page always wins.
  • CFE doesn’t publish Tulum’s tariff on a page we could find, so we don’t state one — your bill shows yours.
  • CFE doesn’t publish the Tulum office’s opening hours, so we don’t guess them.
  • Amounts are CFE’s published figures when we checked: reconnection fees include 16% VAT; the guarantee deposit carries no VAT.
  • This is general information, not legal advice. For a dispute with CFE, Profeco is the official consumer agency.

Every section links the page it comes from. Each was opened and checked on the date shown.

Show all 29 sources
  1. Reporte de fallas en el suministro de energía eléctricaCFE · Checked October 11, 2026
  2. Reporte de No Luz (PDF)CFE · Checked October 11, 2026
  3. Comisión Federal de Electricidad — Atención al cliente 071, CFE Contigo y Mi CFECFE · Checked October 11, 2026
  4. CFE ContigoCFE (App Store) · Checked October 11, 2026
  5. Boletín CFE-BP-024/26: acciones para prevenir incidentes con la infraestructura eléctrica (PDF)CFE · Checked October 11, 2026
  6. Preguntas frecuentesCFE · Checked October 11, 2026
  7. ¿Dónde pagar?CFE · Checked October 11, 2026
  8. Pago del recibo de luz en líneaCFE · Checked October 11, 2026
  9. Conoce tu reciboCFE · Checked October 11, 2026
  10. Derechos y obligaciones del usuario de Suministro BásicoCFE · Checked October 11, 2026
  11. Costo de reconexiónCFE · Checked October 11, 2026
  12. Tarifa DAC (Doméstica de Alto Consumo)CFE · Checked October 11, 2026
  13. Boletín CFE-BP-050/26: inicia apoyo de tarifas de verano (PDF)CFE · Checked October 11, 2026
  14. Para contratarCFE · Checked October 11, 2026
  15. Contratación para clientes de tarifa doméstica (PDF)CFE · Checked October 11, 2026
  16. Depósitos de garantía — tarifas domésticasCFE · Checked October 11, 2026
  17. Terminación de contrato por finiquito (PDF)CFE · Checked October 11, 2026
  18. Centros de Atención a Clientes (localizador)CFE · Checked October 11, 2026
  19. Reporte de aparatos dañados (PDF)CFE · Checked October 11, 2026
  20. Concilianet — proveedores participantes (CFE incluida)PROFECO · Checked October 11, 2026
  21. Profeco recuerda sus medios de contacto (9 de junio de 2026)PROFECO · Checked October 11, 2026
  22. Contrato de interconexión para hogarCFE · Checked October 11, 2026
  23. Contratación de suministro para solicitudes de interconexión (PDF)CFE · Checked October 11, 2026
  24. Preguntas frecuentes sobre generación distribuidaComisión Nacional de Energía · Checked October 11, 2026
  25. Comisión de Agua Potable y Alcantarillado — Paga tu reciboCAPA Quintana Roo · Checked October 11, 2026
  26. Instalación de toma (contrato del suministro de agua potable y saneamiento) — QROO-CAPA-TS-005Gobierno de Quintana Roo — CAPA · Checked October 11, 2026
  27. Precios máximos aplicables de Gas LPComisión Nacional de Energía · Checked October 11, 2026
  28. Profeco recuerda sus vías para recibir denuncias y quejasPROFECO · Checked October 11, 2026
  29. Recomendaciones a la población ante la presencia de huracanesSEMARNAT · Checked October 11, 2026

Something here out of date? Tell us